In order to reduce time and cost, the general contractor (Turner Construction) for this Hilton Garden Inn, retained Kerkstra / Spancrete Great Lakes (Jenison, MI) to fabricate precast wall panels and floor plank for the project. 8" CMU bearing walls were originally specified on the construction documents. The use of 8" precast wall panels saved the project valuable construction time with no cost impact.
We at Reigstad & Associates, having extensive experience in both precast concrete and high-rise design, were able to provide Kerkstra with economical and practical solutions for ease of fabrication and erection.
Reigstad & Associates received notice to proceed on 1-20-03 and were able to complete erection drawings by 2-10-03. Thats erection drawings done in 3 weeks for a 10-story hotel. Shop tickets were then completed for fabrication on 3-3-03.
Precast solution included approximately 110,000 square feet of floor and roof plank and 327 wall panels.
Kerkstra / Spancrete Great Lakes is very pleased with the
attention to detail and follow through on numerous issues by Reigstad.
"Reigstad & Associates did an outstanding job on a very difficult 10 story
building. They overcame numerous obstacles converting a masonry structure to precast;
requiring they work closely with the architect, contractor, ourselves and the erector to
coordinate and follow through on all aspects of a precast project. All this was
accomplished from our initial kickoff meeting to start of production in ten weeks. Our
hats off to the staff of Reigstad & Associates." - Greg Kerkstra, President
Kerkstra / Spancrete Great Lakes.